| Project name : |
Unilever Distribution Centre CCS 2 |
| Construction floor area : |
62,000 m2 |
| Total No. of Units : |
N/A |
| No. of floor : |
1 floor |
| Project start : |
April 2013 |
| Project complete : |
November 2014 |
| Client : |
Thai Consumer Distribution Centre Company Limited |
| Project detail: |
New Distribution Centre for Unilever Featuring:-
- 64 docks with manual leveller
- 5 tonne/m2 floor load
- FM2 flat floor
- 23m high roof
|
| Cornerstone role : |
Project Management and Quantity Surveying Services |